Polihali project delayed to 2027

The long-delayed M37 billion Lesotho Highlands Water Project (LHWP) – facing funding pressures, COVID-19 delays and protests – will begin water delivery in 2027.

Responding to questions from Reuters, the RSA Department of Water and Sanitation said the building of roads, accommodation and electricity installations had begun, and that border closures due to COVID-19 would not have a “material impact”.

“COVID-19 disruptions aren’t expected to have a material impact on the planned completion date of project works and commencement date of water delivery to South Africa, in early 2027.”

Created in 1984, the LHWP was designed to have five phases over 30 years and transfer up to 2 billion cubic meters of water annually from Lesotho to South Africa’s commercial hubs and industries like Sasol and Eskom.

Phase one started delivering water in 1996. Phase two, which includes the 2.3 billion cubic metre Polahli Dam and a 1,200 megawatt hydro-electric plant in Lesotho, was meant to be complete by 2020.

The department said the 60 billion rand needed by the Trans-Caledon Tunnel Authority (TCTA), South Africa’s state-owned company responsible for the Lesotho project, would be generated through further debt issuance.

“TCTA is planning a debt capital markets programme in the near future to complement funding of capital expenditure and possible long-term refinancing of shorter-dated maturities,” the department said.

In 2019 and 2020 water supply to Gauteng was periodically throttled as a result of severe drought related to climate change and creaking infrastructure due to funding shortfalls for maintenance and new projects.

Bitter disagreements over compensation and job reservations between Lesotho officials and the communities that need to be relocated to make way for construction, around 500 households in 35 villages, led to protests in January and February, threatening to lengthen delays.

Two Lesotho community organisations told Reuters they were considering further protests and legal action against the Lesotho Highlands Development Authority (LHDA). The LHDA did not respond to written questions from Reuters. (Reporting by Mfuneko Toyana; editing by Jonathan Oatis)

-Reuters

Hot this week

T-Connect celebrates Earth Day  

Digital transformation group, T-Connect, on Wednesday this week celebrated...

Woman seeks to evict son for alleged abuse

The Matala Local Court has heard a case in...

Jubilation as Senqu Bridge is officially opened

King Letsie III says the unveiling of Senqu Bridge...

Community demands benefits from water project

Residents of Malingoaneng in Mokhotlong have called on the...

Court bid to scrap electricity tariff hikes

The High Court has heard a case in which...

Topics

T-Connect celebrates Earth Day  

Digital transformation group, T-Connect, on Wednesday this week celebrated...

Woman seeks to evict son for alleged abuse

The Matala Local Court has heard a case in...

Jubilation as Senqu Bridge is officially opened

King Letsie III says the unveiling of Senqu Bridge...

Community demands benefits from water project

Residents of Malingoaneng in Mokhotlong have called on the...

Court bid to scrap electricity tariff hikes

The High Court has heard a case in which...

Petroleum Fund engages media to demystify pricing

Petroleum Fund has held a strategic dialogue and capacity building engagement...

ROLL to handover dip

The Regeneration of Landscapes and Livelihoods (ROLL) project will officially handover...

Lesotho joins global campaign to boost vaccine coverage

Lesotho will roll out life-course vaccination services at all health facilities...
spot_imgspot_imgspot_imgspot_img

Related Articles

Popular Categories

spot_imgspot_imgspot_imgspot_img
0
Would love your thoughts, please comment.x
()
x