Museum nearing completion

By Neo Kolane

Construction of the National Art Museum is 85 percent complete, with the remaining 15 percent reserved for specialist sub-contractors.

The project of the museum construction began in December 2015 and was expected to be complete in December 2017 but has suffered a significant delay.

The actual construction of the project started at a cost amounting to M111-million but as of now the cost has ballooned to over M170-million; it is projected to skyrocket to M240-million.

Speaking during a tour of the museum today, the site agent of Sigma Construction, Tlotliso Liphoto said there have been challenges that the project faced, such as cash flow problems.

“Getting funds from elsewhere was also a challenge, as well as changing of the design and the specialist to be attached to subcontractors after the lockdown, which resulted in an increase in prices of materials for construction.

“But we believe that we will finish the project before the end of the year, which is the deadline for completion,” Liphoto said.

Hot this week

M-Pesa renews partnership with Maletsunyane Braai Festival 

VCL Financial Services, the operator of M-Pesa in Lesotho, has...

Senqu Basin survey begins

A survey on Senqu River and its major tributaries commenced yesterday and will...

Drones tackle medicine shortage

Government is partnering with United States-based drone delivery company...

20-year marriage ends in bitter court battle

A 20-year marriage has descended into a bitter legal...

LEWA clears way for seven rural mini-grid projects

The Lesotho Electricity and Water Authority (LEWA) has granted...

Topics

M-Pesa renews partnership with Maletsunyane Braai Festival 

VCL Financial Services, the operator of M-Pesa in Lesotho, has...

Senqu Basin survey begins

A survey on Senqu River and its major tributaries commenced yesterday and will...

Drones tackle medicine shortage

Government is partnering with United States-based drone delivery company...

20-year marriage ends in bitter court battle

A 20-year marriage has descended into a bitter legal...

LEWA clears way for seven rural mini-grid projects

The Lesotho Electricity and Water Authority (LEWA) has granted...

‘If democracy can’t put bread on the table, let it go’

Speaker of the National Assembly, Tlohang Sekhamane, has warned...

M400 loan facility struggles for uptake

. . .  only M19m disbursed from IGF so...

RSL trains journalists on tax reporting

Revenue Services Lesotho (RSL) has held a two-day media training workshop under the theme, “Strengthening Tax...
spot_imgspot_imgspot_imgspot_img

Related Articles

Popular Categories

spot_imgspot_imgspot_imgspot_img
0
Would love your thoughts, please comment.x
()
x