LHDA Diversion Tunnel JV awarded

The Lesotho Highlands Development Authority (LHDA) has awarded the contract for the construction of the Polihali diversion tunnels to SCLC Polihali Diversion Tunnel JV, marking another significant step in the implementation of Phase II of the Lesotho Highlands Water Project (LHWP).

The tunnels, one 7m in diameter and almost a kilometre in length, and the second, 9m in diameter and almost a kilometre long, run parallel to each other from the intake point to the outlet downstream of the dam.

The tunnels will be excavated by drill and blast method, and will be supported by rockbolts and shotcrete as required. The SCLC Polihali Diversion Tunnel JV combines international, South African and Lesotho expertise: Salini Impregilo S.p.A (South African branch), Cooperativa Muratori Cementistri CMC di Ravenna (South African branch), LSP Construction (Pty) Ltd. (Lesotho) and CMI Infrastructure Ltd (South Africa).

The contractor is expected to be on site in April with the works expected to be completed in approximately 18 months. The project cost is estimated at M517 million.

“The diversion tunnels are essential to facilitate the construction of the Polihali Dam. Their construction is an important element of the advance infrastructure works which started towards the end of 2018 with the awarding of the contracts for the Polihali North East Access road and the civils work at Katse and Mokhotlong. The advance infrastructure will largely be completed prior to commencement of construction of the Polihali dam and the Polihali to Katse water transfer tunnel,” confirms Tente Tente, the LHDA’s Divisional Manager, Phase II.

Diversion tunnels divert water away from the natural river bed to create a dry foundation and work area needed for the construction of a dam. Their construction usually goes along with the building of cofferdams, one upstream and one downstream of the proposed dam, which together allow the river flow to bypass the dam foundation area.

In the case of the Polihali Dam, two diversion tunnels will be constructed to divert the waters of the Senqu River. Building two tunnels will increase the capacity to carry floods and will provide flexibility to work in one tunnel while the river flows in the other one.

The Metsi a Senqu-Khubelu Consultants Joint Venture (MSKC) which also includes a number of South African and Lesotho-based firms i.e. Aurecon (SA), Knight Piesold (SA), Hatch Goba (SA), SMEC (SA) and FM Associates (Lesotho), has designed the diversion tunnels and will also supervise the construction work.

Phase II of the Lesotho Highlands Water Project builds on the successful completion of Phase I in 2003. It delivers water to the Gauteng region of South Africa and utilises the water delivery system to generate hydro-electricity for Lesotho. Phase II will increase the current supply rate of 780 million cubic metres per annum incrementally to more than 1 270 million cubic metres per annum.

At the same time, it will increase the quantity of electricity generated in Lesotho and is a further step in the process of securing an independent electricity source to meet Lesotho’s domestic requirements. The hydropower further feasibility studies have confirmed that conventional hydropower is the preferred option. Three potential conventional hydropower sites have been identified: two on the Senqu River and one at Oxbow. The studies on these are being taken to bankability stage.

-Tunneling Journal

Hot this week

Association strengthens media coverage of wool and mohair

A two-day media training workshop will be held this...

Rural women fight for their rights

Rural women have called for greater access to information,...

Entrepreneur strives to build made in Lesotho brand

A 29-year-old entrepreneur from Baroeng in Botha-Bothe is turning...

2nd Legacy Leadership Summit 2026 underway

The 2nd Legacy Leadership Summit 2026 is underway in...

Tau joins SADC talks

The Minister of Foreign Affairs and International Relations, Limpho Tau, yesterday...

Topics

Association strengthens media coverage of wool and mohair

A two-day media training workshop will be held this...

Rural women fight for their rights

Rural women have called for greater access to information,...

Entrepreneur strives to build made in Lesotho brand

A 29-year-old entrepreneur from Baroeng in Botha-Bothe is turning...

2nd Legacy Leadership Summit 2026 underway

The 2nd Legacy Leadership Summit 2026 is underway in...

Tau joins SADC talks

The Minister of Foreign Affairs and International Relations, Limpho Tau, yesterday...

Media training on EU trade deal

The Ministry of Trade, Industry and Business Development will next week host...

Lesotho to commemorate Armistice Day 

Lesotho will tomorrow commemorate Armistice Day at Makoanyane Square in Maseru. The event...

M80k up for grabs at Mokoari Tourism Festival

Mokhotlong is hosting the Mokoari Tourism Festival at Malingoaneng Race Course today,...
spot_imgspot_imgspot_imgspot_img

Related Articles

Popular Categories

spot_imgspot_imgspot_imgspot_img
0
Would love your thoughts, please comment.x
()
x